We have considered the various high priority issues in the building and prepared several packaged scenarios for consideration.
Importantly these combinations of work items are not prescriptive, and at the district’s direction we can prepare alternative combinations of the work to your preferences.
A project including roofing, gym masonry, HVAC + fresh air, and lower locker drainage accomplishes the most critical areas within the estimated budget.
Roofing & Masonry Focused
• Lower and 3rd floor roofing
• Gym, Boiler room/Shop, and 3-story masonry
HVAC Focused
• Full 3 story HVAC systems
• Fresh Air & humidity control for entire site
Restroom Focused
• Gym restrooms
• 1st floor restrooms
• 2nd floor restrooms
• Lower locker drainage
• Lower locker restoration
Limited envelope & restrooms
• All roofing
• Gym & boiler room/shop masonry ex-3 story masonry
• All restrooms ex-lower locker rooms
All Envelope, limited restroom
• All roofing & Masonry
• Gym & 1st floor restrooms, ex-3 floor restrooms
• Lower locker drainage ex-restoration
Roofing, limited masonry & restrooms, All HVAC
• All roofing & limited masonry
• All restrooms ex-lower-level locker room
• All HVAC including fresh air
Estimates are considered directionally accurate for the purposes of budgetary discussions.